Upon meeting with Walsh and speaking with several of the subcontractors, we have decided to change the traffic switch-over date to Tuesday July 26th.
The sign company will be in Wednesday and Thursday to install all remaining signs. Safety is a our #1 priority so we feel this is the best decision.
Bell Traffic also needs to cut the loops for the cottage/East Central St intersection which will be done Wednesday. This will ensure all signals are operational per designed plan.
Please let me know if you have any other questions. I do NOT foresee us changing the July 26th date.
I will change the (3) state message boards we have up now. If the police could change their 2 that would be appreciated.
Thank You,
Anthony Tavalone
CE III MA DOT
(617) 233-0795
![]() |